The Los Cabos municipal government and its water utility OOMSAPAS are building a new water transmission line in Cabo San Lucas, a 16.9 million peso (roughly $850,000 USD) project designed to improve supply for more than 42,000 residents in the city’s growing neighborhoods.

The pipeline runs from the Medical Corridor to Tank 1000 in the Lomas del Sol neighborhood. It consists of 2,000 linear meters of 300mm (12-inch) high-density polyethylene (HDPE) pipe and will connect to the existing La Sanluqueña pump station line. OOMSAPAS, the Municipal Water, Sewerage and Sanitation Operating Agency of Los Cabos, is overseeing the work in coordination with FISAM, the environmental sanitation trust.

Construction Active Near Tierra and Rayo Streets

Active construction is currently underway at the intersection of Tierra and Rayo streets. Drivers and residents in that corridor should expect localized traffic disruptions and possible access delays while the work continues.

Advertise with Baja Daily News

The new line is intended to improve water distribution capacity across the Cabo San Lucas delegation by strengthening the connection between existing pump infrastructure and elevated storage. Low water pressure and intermittent supply have been longstanding complaints in several colonias on the city’s expanding edges.

Part of a Broader Push on Water Infrastructure

This project is one piece of a larger investment in Cabo San Lucas water infrastructure. According to the Los Cabos municipal government, five water projects totaling roughly 80 million pesos (about $4 million USD) are moving forward in the city, with combined benefits reaching more than 65,000 residents.

Cabo San Lucas faces persistent water stress driven by rapid population growth and tourism development. OOMSAPAS has also been evaluating whether to reallocate part of San José del Cabo’s water supply to ease shortages during the hottest months. The city’s existing desalination plant contributes about 120 liters per second to the system, and a second plant is under construction on the north side of Cabo San Lucas. That facility, expected to be operational by late 2026, will produce 250 liters per second drawn from the Pacific Ocean.

What Residents Can Expect

For property owners and renters in Lomas del Sol and surrounding neighborhoods, the new pipeline should mean more consistent water pressure once the line is connected and operational. No completion date has been announced, but the project is actively under construction.

This story was first reported by the Los Cabos municipal government through its official website, loscabos.gob.mx.